April 8, 2003

The footings were poured with concrete on April 7th.  Phil Martin, the mason, is inspecting and getting ready to start laying concrete block.     

April 10, 2003

The mason crew is putting up concrete block.  The outline of the house is now more evident.  

(Click on the photo or here for a larger view.)     

April 14, 2003

More concrete is delivered as the walls go up.  

(Click on the photo or here for a larger view.)     

May 12, 2003

The outbuilding footings are in.  Mark likes what he sees.      

(Click on the photo or here for a larger view.)     